The Lianozovo station on the Lyublinsko-Dmitrovskaya metro line is almost a quarter completed

The readiness of the future Lianozovo station under construction on the Lyublinsko-Dmitrovskaya line of the Moscow Metro is estimated at 23%, said the Deputy Mayor of Moscow in the government of Moscow on urban policy and the construction Andrey Bochkarev. Mosinzhproekt Engineering Holding is the managing company to construct new lines and stations of the Moscow Metro.

Today, all three stations of the new section of the “pale green”metro line are in the active construction stage. At Lianozovo, the enclosing structures are ready, the excavation and the excavation bracing are being completed, and the in situ concrete works are underway. The overall construction readiness of the station is estimated at 23%,” said Andrey Bochkarev.

According to him, based on the station’s future, it is planned to create a transport hub with D-1 and the routes of urban ground transport.

Mosinzhproekt

The Deputy Mayor also clarified that the excavation is completed at the neighboring station of the line section under construction, 800 Years of Moscow Street station. The remaining excavation work will be carried out after the completion of tunneling.

“At the future Fiztech terminus station, works are being carried out on the preparatory phase of installing the enclosing structures of the pit using diaphragm wall technology and the removal of utilities from the construction site,” added Andrey Bochkarev.

We recall, the General Director of Mosinzhproekt JCS Juri Kravtsov said 1,473 meters of the right running tunnel and 1,272 meters of the left running tunnel from the planned 2,345 meters already passed between the future Lianozovo station and Fiztech station. The Klavdia tunneling machine, erecting the right running tunnel between the 800 Years of Moscow Street station and Lianozovo station, has overcome more than 1,000 m out of 1,800 meters.

It is assumed that the extension of the pale green line to the Severny village will improve transport accessibility for residents of the following districts such as Dmitrovsky, Eastern Degunino, Lianozovo, and the Severny village. It is expected, when the new section is commissioned, they will be able to save up to 20 minutes when traveling around the city.